Classroom & Office Building 3
Planned classroom and office facility for the growing academic core.
- Budget: $75 million
- GSF: 60,000
- Delivery: Design-build
- Completion: December 2027
Major campus projects
Review the map for project locations, then use the project cards for known budget, size, delivery method, completion timing, and source links.
Planned classroom and office facility for the growing academic core.
Field education and research facility supporting campus academic and environmental work.
Major academic project connected to medical education programming.
Student housing project adding beds near the campus core.
| Project | Budget | GSF | Delivery | Completion |
|---|---|---|---|---|
| Classroom & Office Building 3 | $75 million | 60,000 | Design-build | December 2027 |
| Field Education & Research Center | $4.8 million | 3,364 | Design-bid-build | Fall 2025 |
| Medical Education Building | $300 million | 203,500 | CM at Risk | Fall 2026 |
| Promise Housing | $100 million | 125,000 | Design-build | August 2026 |
Total listed budget: $479.8 million.